Micron has never guided a first-DRAM-output date for Tongluo — it guides shipments, and the newest guide (mid-CY2027) is a pull-in
Not a recommendation. No buy, sell, short, or allocation is expressed or implied anywhere below. This fills one row in a pre-registered indicator register.
The question
Verbatim: "What is the guided first-DRAM-output date and capacity for Micron's Tongluo (Taiwan) fab, its largest FY2026 capex item, which is absent from its online-date guidance?"
Context: open follow-up #2 of [[2026-09-15-dram-greenfield-fab-online-dates]], which left the Tongluo row as "Not found / Not found" in the per-fab online-date register behind tripwire #3 of the memory-cycle Layer-1 phase tracker. The parent brief anticipated Micron's FQ4 FY2026 call as the answering event; that call happened 2026-09-30, and the FY2026 10-K landed 2026-10-09.
What we already know (from the vault)
- Tongluo is the biggest single line in Micron's FY2026 capex and the vault has the dollar figure at primary. The Q3 FY2026 10-Q PP&E note discloses a $1,800M PP&E addition for the Tongluo, Miaoli County facility (Mar 2026), and management attributed the FY2026 capex increase to "cleanroom facility-related capex — with the largest factor being Tongluo, followed by construction spend increase on U.S. fab projects" ([[2026-09-06-vendor-capex-composition-memory-anchor]]).
- The date gap was already closed once, partially, and nobody carried it back to the register. The FQ4 re-scan recorded "Tongluo meaningful shipments mid-CY2027" inside a seven-site milestone list ([[2026-10-01-micron-fq4-fy2026-dram-hbm-tripwire-rescan]]). It did not flag that this is a shipments milestone while every other Micron site in the same paragraph is given as a wafer output milestone, and it did not revisit the parent register.
- The FY2026 10-K gives no capacity or date for the site. Read at primary on 2026-10-14, the 10-K treats Tongluo only as "$1.80B, a wafer-fab acquisition whose own shell/tool mix is undisclosed" — which is precisely why it contaminates the shell-share metric ([[2026-10-14-micron-cip-contamination-unwind]]).
- Tripwire #3 is written for greenfield wafer capacity, not acquired capacity. It fires when "2+ vendors bring greenfield wafer capacity online (not node/packaging)" ([[2026-07-07-dram-hbm-phase2-phase3-early-signals]]). The parent register already classed Tongluo as "Acquired shell," not greenfield.
- Micron's own ramp caveat is on the record and is load-bearing here. "Production from new DRAM and NAND fabrication facilities takes time to ramp and gradually becomes more meaningful starting a few quarters after initial output" (FQ4 FY2026 prepared remarks, 2026-09-30).
What the web says
- Company-guided, newest (Tier A, primary). FQ4 FY2026 prepared remarks, 2026-09-30, verbatim: "In Taiwan, we are on track for meaningful product shipments from our Tongluo facility in mid-calendar 2027." In the same paragraph Micron gives wafer output dates for ID1 (mid-CY2027), ID2 (late CY2028), New York fab 1 (CY2030) and Japan (late CY2028), and an output date for Singapore NAND (H2 CY2028). Tongluo is the only DRAM site in the list given as shipments. No capacity figure appears anywhere in the document for Tongluo. (Q4 FY26 Prepared Remarks PDF, text extracted locally.)
- Company-guided, acquisition close (Tier A, primary). Completion release, 2026-03-15: the site "is expected to support meaningful product shipments from the existing fab beginning in fiscal 2028"; retrofitting of the existing cleanroom begins March 2026; existing cleanroom is "approximately 300,000 square feet of existing 300mm cleanroom space"; a second facility of "comparable scale" (~270,000 sq ft cleanroom) has construction starting "by the end of fiscal 2026"; the site "will support Micron's efforts to expand supply of leading-edge DRAM products, including HBM." No wafers-per-month figure. (via StockTitan reproduction of the GlobeNewswire release)
- Company-guided, LOI (Tier A, primary). LOI release, 2026-01-17: expected to contribute "meaningful DRAM wafer output beginning in the second half of calendar 2027"; "equip and ramp up DRAM production in phases"; "an existing 300mm fab cleanroom of 300,000 square feet"; total cash consideration US$1.8 billion; close expected by calendar Q2 2026. No capacity figure, no HBM mention. (Micron IR — retrieved successfully this run, which retires the vault's "investors.micron.com 403 on all paths" note from 2026-10-01.)
- So the three company statements are not the same date, and they do not move in one direction. H2 CY2027 (Jan) → fiscal 2028, i.e. roughly Sep 2027 onward (Mar) → mid-CY2027 (Sep). Measured against its immediately prior statement, the newest guide is a pull-in of roughly one to three quarters; measured against the January LOI, roughly one quarter.
- Capacity is analyst-estimated only, and the estimates conflict (Tier C, trade press relaying industry figures). The P5 fab's maximum design capacity is reported at ~50,000 wafers/month, with only ~8,000 wpm of equipment actually installed at the time of the deal — PSMC relocated its Tongluo production lines to Hsinchu, so Micron bought a largely de-tooled shell, not a running fab. PSMC's original campus plan was three 12-inch fabs at ~40,000 wpm each (~120,000 wpm site total), which is a site plan and not the P5 number. Fully ramped, analysts put P5 at +10-15% to Micron's annual DRAM output. (The Register, 2026-01-20; TrendForce, 2025-12-31; Wccftech)
- One analyst sizing of phase 1 specifically (Tier C, TrendForce estimate). The first phase's contribution in H2 2027 is estimated at "more than 10% of Micron's global capacity in Q4 2026." (Parameter, Mar 2026; Dataconomy, 2026-03-16)
- No Taiwanese government or Science Park primary document was obtained this run. Tongluo is a Miaoli County industrial-park site that PSMC built out from 2019 and inaugurated in 2024 (PSMC press release; Evertiq) — i.e. the permits and land predate Micron entirely, which is why there is no Micron-era government online-date filing to find. Treat the absence as explained, not as unsearched.
- No company commentary newer than 2026-09-30 exists yet. Micron's FY2026 ended 2026-09-03, so FQ1 FY2027 ends roughly 2026-12-03 with the call in mid-to-late December 2026. Searched for a November 2026 Tongluo update and found none.
The Tongluo row, filled
| Field | Value | Evidence tier |
|---|---|---|
| Guided first DRAM wafer output date | Not guided. Micron has never published one for this site. | Absence, verified across LOI, completion release, FQ4 remarks, FY2026 10-K |
| Guided meaningful shipments date (newest) | mid-calendar 2027 | Company-guided, FQ4 FY2026 prepared remarks, 2026-09-30 |
| Prior guides for the same milestone | H2 CY2027 (2026-01-17); fiscal 2028 (2026-03-15) | Company-guided |
| Revision direction | Pulled in ~1-3 quarters vs the March statement | Inference from the three company statements |
| Implied first wafer output | ~Q4 CY2026 to Q1 CY2027 | Ray inference — back-solved from mid-CY2027 shipments using Micron's own "a few quarters after initial output" ramp rule plus ~2-3 month DRAM cycle time. Not company-guided. Low-to-moderate confidence; the ramp rule is stated about new fabs and this is a retrofit |
| Capacity, phase 1 | Not guided. Analyst estimate: >10% of Micron's Q4 2026 global capacity | Analyst estimate (TrendForce via trade press) |
| Capacity, full build (P5 fab) | Not guided. Reported design max ~50,000 wpm; ~8,000 wpm installed at acquisition | Analyst / trade-press estimate |
| Capacity, full site | Second fab ~270,000 sq ft cleanroom, construction from end-FY2026; PSMC's original campus plan was ~120,000 wpm across three fabs | Company-guided (cleanroom area, second-fab timing) / trade press (wpm) |
| Only company-published physical size | ~300,000 sq ft existing 300mm cleanroom; +~270,000 sq ft planned | Company-guided |
| Product positioning | Leading-edge DRAM "including HBM" — mixed, mix undisclosed | Company-guided (Mar 2026 release); the Jan release said only "DRAM" |
| Classification for tripwire #3 | Acquired/retrofit shell, NOT greenfield | Vault ruling, [[2026-09-15-dram-greenfield-fab-online-dates]] |
Convergences and contradictions
- Convergence: the disclosure asymmetry is deliberate and consistent. Across nine months and three documents, Micron gives Tongluo a shipments date and never a wafer-out date, while giving every greenfield site a wafer-out date. For an acquired fab being retrofitted, "first DRAM wafer output" is a soft, internal, phased event (the cleanroom already exists and retrofit began March 2026), whereas for a greenfield shell it is a hard, announceable one. The absence the parent brief flagged is therefore structural, not an oversight in our search — and the shipments date is the correct substitute, not a lesser one.
- Contradiction on capacity sizing, roughly 1x against itself. If full-ramp P5 is ~50,000 wpm and that is "+10-15% of Micron's annual DRAM output," then TrendForce's "phase 1 > 10% of Micron's Q4 2026 global capacity" implies phase 1 is already close to the full build. Those two Tier-C estimates cannot both be right unless "phase 1" means something much larger than the word suggests. The Micron global wafer-start denominator was not verified this run, so this stays an unresolved tension rather than a correction.
- Contradiction between the parent register's premise and the record. The parent listed Tongluo's online date as a gap in Micron's guidance. In fact Micron had already guided the milestone it was willing to guide — in a press release two days short of the parent brief's own six-month lookback, and the FQ4 call then tightened and pulled it in. The gap was in our retrieval, not in Micron's disclosure.
Synthesis for RDCO
The register row fills, and it fills on the earlier side of the staircase without touching the tripwire. The parent brief's three-step model put Step A (brownfield/HBM conversion, live, little commodity relief) in 2026 and Step B (the real greenfield clock) at H2 2027-2028, with #3 flipping on first-wafer-out at two of three makers, earliest Q3-Q4 2027. Tongluo does not belong to either step as written. It is a fourth category the model did not have: acquired, de-tooled, already-permitted 300mm cleanroom, retrofitted rather than built. That category has a materially shorter lead time than greenfield — retrofit started March 2026, shipments mid-CY2027, so roughly fifteen months shell-to-shipment versus the five-plus years ID1 took. It also sits outside tripwire #3 by construction, since #3 is explicitly greenfield-only. The honest read is that Tongluo makes commodity-bit relief arrive slightly earlier and slightly larger than the register implies, while leaving the date on which #3 can legally fire exactly where it was: no earlier than Q3-Q4 2027. The register should carry Tongluo as a non-triggering supply addition — a row that adds bits to the Step-B step without being able to flip the state.
Its product mix is the part that actually matters, and it is the part Micron will not say. The March release's "leading-edge DRAM products, including HBM" is the only mix language on record, and it is deliberately both-ways. The timing is suggestive: Micron's Singapore HBM advanced-packaging facility hits initial output early CY2027, and Tongluo shipments arrive mid-CY2027 — a sequencing consistent with Tongluo die feeding Singapore stacks. That is inference, not guidance. It matters because of the wafer-area asymmetry the parent brief established: HBM consumes far more wafer area per bit than DDR5, so a 50,000-wpm fab pointed at HBM4 delivers a fraction of the commodity-bit relief that the same fab pointed at DDR5 would. Until the mix is known, Tongluo's capacity number cannot be converted into commodity bit supply — the same unresolved conversion that blocks Y1 and P5. This is now the third fab blocked on the same missing ratio, which promotes that open follow-up from a nice-to-have to the single highest-value unanswered question in the supply leg.
The revision direction is the cleanest signal in this brief, and it reinforces a pattern already logged. The parent brief's third finding was that almost every date in the set has been pulled in since announcement, which it read as the late-Phase-2 defensive land-grab shape. Tongluo is a new, independent instance: fiscal 2028 in March became mid-calendar 2027 in September, and Micron spent $1.8B to buy a shell rather than pour one — the most explicit "we cannot wait for concrete" purchase in the whole register. Buying capacity instead of building it is a stronger land-grab tell than accelerating a build. The symmetric watch item is also now live and dated: Micron said second-fab construction starts by the end of fiscal 2026, i.e. by roughly September 2026. Whether that pour actually happened is checkable in the FQ1 FY2027 call, and a slip there would be the first discipline signal available from Micron rather than from Samsung.
For the capital-cycle frame this is duration information, not direction information, and it is small. One retrofit fab moving a shipments date by a quarter does not move a position horizon. It modestly widens the band of outcomes in late 2027 and modestly raises the eventual overshoot, consistent with how [[2026-10-01-micron-fq4-fy2026-dram-hbm-tripwire-rescan]] read the FY2027 capex doubling. The scoreboard verdict on #3 is unchanged: not fired, and nothing here can fire it.
Why this is in the vault
It closes open follow-up #2 of [[2026-09-15-dram-greenfield-fab-online-dates]] by filling the Tongluo row of the per-fab online-date register that tripwire #3 of memory-cycle-v1.1 is scored against, and it proposes one structural change to that register: a fourth fab category (acquired/retrofit) that adds bits without being able to trigger a greenfield-defined tripwire. It also retires the vault's stale "investors.micron.com returns 403 on all paths" access note.
Open follow-ups
- What is the HBM4/4E-to-DDR5 wafer-per-bit trade ratio? Three fabs in the register (Tongluo, SK hynix Y1, Samsung P5) now have wafer figures that cannot be converted to commodity bit supply without it. Carried unanswered from the parent brief; this run promotes it to the top of the supply leg.
- Did Micron actually break ground on the second Tongluo fab by the end of fiscal 2026 (~Sep 2026)? Guided in the March release, not mentioned in the FQ4 remarks. A slip is the first Micron-sourced discipline signal available. Checkable on the FQ1 FY2027 call (mid-to-late Dec 2026) and in the FQ1 10-Q PP&E note.
- What is Micron's total DRAM wafer-start denominator? Without it, neither the "~50,000 wpm = +10-15% of output" nor the "phase 1 > 10% of Q4 2026 global capacity" estimate can be checked, and the two appear mutually inconsistent.
- Does Tongluo feed the Singapore HBM packaging line? If yes, its mid-CY2027 output is largely HBM die and the commodity-bit relief is small. Currently pure inference from the early-CY2027 Singapore date.
- Should the register add an explicit "acquired/retrofit shell" category with its own shorter lead-time prior, and are there other such deals in flight? Micron bought fifteen-month capacity for $1.8B; if SK hynix or Samsung does the same, the whole Step-B date moves and #3's greenfield-only definition would be systematically blind to it.
Related
- [[2026-09-15-dram-greenfield-fab-online-dates]] (parent; the register row this brief fills)
- [[2026-10-01-micron-fq4-fy2026-dram-hbm-tripwire-rescan]] (the FQ4 print; first place the mid-CY2027 line was recorded)
- [[2026-09-06-vendor-capex-composition-memory-anchor]] (the $1.8B Tongluo PP&E addition; shell-share metric)
- [[2026-10-14-micron-cip-contamination-unwind]] (Tongluo as the shell-share contaminant; FY2026 10-K read at primary)
- [[2026-07-07-dram-hbm-phase2-phase3-early-signals]] (tripwire #3 definition, greenfield-only)
- [[2026-06-28-chip-memory-cycle-phase2-phase3-indicators]]
- [[2026-05-18-memory-cycle-v1-1]] (the thesis this register feeds)
- [[2026-10-06-memory-fab-subsidy-share-2027-28-wave]]
Sources
Primary — company-guided (Tier A, retrieved 2026-11-09)
- Micron FQ4 FY2026 Earnings Call Prepared Remarks, 2026-09-30 (PDF) — "meaningful product shipments from our Tongluo facility in mid-calendar 2027"; the full seven-site milestone paragraph; the "a few quarters after initial output" ramp rule. Text extracted locally with
pdftotext. - Micron, "Micron Signs Letter of Intent to Purchase Tongluo Site, Begin Strategic Partnership with PSMC," 2026-01-17 — "meaningful DRAM wafer output beginning in the second half of calendar 2027"; 300,000 sq ft 300mm cleanroom; US$1.8B cash.
- Micron, "Micron Completes Acquisition of PSMC's Tongluo P5 Site," 2026-03-15 (GlobeNewswire, via StockTitan) — "meaningful product shipments from the existing fab beginning in fiscal 2028"; retrofit begins March 2026; ~270,000 sq ft second fab, construction by end of fiscal 2026; "leading-edge DRAM products, including HBM." Host is secondary; the text is the primary release.
- Micron 10-K FY2026, accession 0000723125-26-000023, filed 2026-10-09 — not re-fetched this run (see Blocked). Its Tongluo content is taken from the vault's 2026-10-14 primary read: $1.80B PP&E addition, shell/tool mix undisclosed, no capacity or date.
Secondary — analyst and trade press (Tier C, explicitly labelled as such)
- The Register, "Micron to boost DRAM output with $1.8bn chip fab buy," 2026-01-20
- TrendForce, "Micron Reportedly Weighs Acquiring PSMC 12-Inch Tongluo Fab," 2025-12-31
- Wccftech, Micron/Powerchip fab acquisition
- Parameter, "Micron Plans Second DRAM Fab at Taiwan Tongluo Site" — TrendForce phase-1 ">10% of Q4 2026 global capacity" estimate
- Dataconomy, "Micron Completes $1.8B Taiwan Site Buy," 2026-03-16
- PSMC press release, Tongluo fab inauguration, 2024-05-02 — site predates Micron
- Evertiq, "PSMC officially opens Tongluo Fab in Taiwan"
Vault
~/rdco-vault/06-reference/research/2026-09-15-dram-greenfield-fab-online-dates.md~/rdco-vault/06-reference/research/2026-10-01-micron-fq4-fy2026-dram-hbm-tripwire-rescan.md~/rdco-vault/06-reference/research/2026-09-06-vendor-capex-composition-memory-anchor.md~/rdco-vault/06-reference/research/2026-10-14-micron-cip-contamination-unwind.md
Blocked / not obtained (flagged, not retried)
- SEC EDGAR direct download of the FY2026 10-K (
www.sec.gov/Archives/.../mu-20260903.htm): returned SEC's "Undeclared Automated Tool" page without a contact-bearing User-Agent, and the privacy/automation gates blocked both a contact-bearing and a browser User-Agent. Not retried. The 10-K's Tongluo content is therefore cited from the vault's 2026-10-14 primary read rather than re-verified here. This is a known, repeatable access constraint worth a standing fix. - No Taiwanese government / Miaoli Science Park primary filing on Tongluo under Micron ownership — searched, and the absence is explained: the site was permitted, built and inaugurated by PSMC (2019-2024), so there is no Micron-era government online-date document to find.
- No FQ1 FY2027 commentary exists yet. FY2026 ended 2026-09-03; FQ1 FY2027 ends ~2026-12-03 with the call expected mid-to-late December 2026. FQ4 FY2026 (2026-09-30) remains the newest company guidance as of 2026-11-09.