Home Rebuild 2027 — Milestones & Decision Gates

Live tracking. Update as items complete or shift.

Q2 2026 (now → Jun 2026) — DISCOVERY

Milestone Owner Status Due Notes
4-point inspection on current home Founder Not started 2026-05-15 ~$200; lays cards on table for insurance + scope
Tampa zoning + flood zone verification (FEMA + City Planning) Both Not started 2026-05-31 Free; 30 min online + zoning verification letter
Apply for $300k HELOC on current home (use as dry powder) Founder Not started 2026-06-30 While MG income still on tax returns; don't draw
Initial parent conversation (their budget, retirement income, target area) Founder Not started 2026-06-30 Determines mortgage qualification path
Tampa CMA from local realtor (validate $1.0M Zestimate) Both Not started 2026-09-30 Real comp-based estimate before planning

Q3 2026 (Jul-Sep) — ANCHOR INCOME + SAVE

Milestone Owner Status Due Notes
phData W-2 starts (June 2026) — first 3 months on the books Founder In progress 2026-09-30 Lender history starts accumulating
HYSA target: $370k by end of Q3 Both In progress 2026-09-30 $77k savings cushion above current
Schedule consultation with Tampa mortgage broker Founder Not started 2026-08-31 Early conversation; understand bonus inclusion rules

Q4 2026 (Oct-Dec) — DESIGN

Milestone Owner Status Due Notes
Hire residential architect for feasibility + concept design Both Not started 2026-10-31 $5-10k; needs to know zoning + lot constraints first
Architect feasibility + schematic delivered Not started 2026-12-15 Determines real cost: $1.5M? $1.8M? $2M+?
HYSA target: $440k by end of Q4 Both Not started 2026-12-31 On track for $490-550k Q1 2027 capital
Initial parent home search begins (their lead, founder advises) Founder Not started 2026-12-31 Keep separate from Tampa build process

Q1 2027 — DECISION GATE

Go/no-go on the full plan based on these criteria:

Criterion Pass condition Status
phData W-2 history ≥7 months on file TBD
HYSA balance ≥$490k TBD
Architect concept + cost estimate Total project ≤ $1.8M TBD
Parents' mortgage qualification Pre-approved on retirement income alone, OR willing for founder to co-sign TBD
Tampa CMA Current home sale value validated at $950k+ TBD
Wife alignment on temp rental for 10-12 months Yes TBD

If all pass: proceed to Q2 2027 execution. If 1-2 fail: delay 6 months, reassess. If 3+ fail: drop to Renovation+Addition (Option A from initial analysis) or hold pattern.

Q2 2027 — EXECUTION KICKOFF

Milestone Owner Status Due Notes
Parents close on $600k retirement home with $150k gift Both Not started 2027-04-30 Parents primary, founder co-signer if needed
List Tampa home with 90-day flexibility Both Not started 2027-03-31 Realtor pre-aligned in Q4 2026
Tampa home under contract Not started 2027-04-30 Bridge financing arranged for build down payment if sale slow
Sign construction contract with builder Both Not started 2027-05-31 Fixed-price contract, not cost-plus
Construction loan closes Both Not started 2027-06-15 Construction-to-perm preferred to avoid two loan closes
Move family into Tampa rental Both Not started 2027-06-30 ~$4k/mo, 12-month lease with go-month-to-month after

Q3 2027 - Q3 2028 — BUILD

Milestone Owner Status Due Notes
Tampa demo + foundation Builder 2027-08-31 First 2 months of build
Framing + dry-in Builder 2027-12-31 Major weather risk window
MEP rough-in Builder 2028-03-31
Drywall + finishes Builder 2028-06-30
Punch list + CO Builder 2028-08-31 Certificate of Occupancy
Move into new home Both 2028-09-30 ~12 months in temp rental total

Ongoing Tracking

Each /finance-pulse monthly run should report:

Notion board has individual tasks for the Q2-Q4 2026 milestones. Future milestones will be queued as their predecessors complete.

Decision Log

Date Decision Reasoning
2026-04-18 Reject "buy temp home + gift later" approach; keep parents' home and Tampa build as separate projects DTI can't hold 2 mortgages + construction loan; gift-with-mortgage is title/tax mess
2026-04-18 Recommend tear-down + rebuild over renovation+addition 1700 sqft 1963 home with 4-point failures + segregated layout makes renovation a half-measure for the cost; tear-down rebuilds completely
2026-04-18 Use $150k gift sizing for parents' down payment Keeps founder's lifetime gift exemption use modest; leaves ~$450k mortgage for parents to carry on retirement income (typical FL retiree mortgage qualification ceiling)
2026-04-18 Target Q1 2027 decision gate, build start Q2 2027 Allows phData W-2 history to season (~7+ months); phases capital accumulation and architect work into supporting roles